Sales representative for Tuscan Village Townhomes is Carolyn Difebo At

 
Color Logo 2014 Newman.jpg
 

Call or Text - 850-685-4013 or email -CarolynYourDestinAgent@Gmail.Com

—- Rear Entry Garage UNITS Available! -—-

END Unit 53 Priced at $469,990

INTERIOR Unit 55 Priced at $434,990

1766 sqft - 3/2.5 - 1 car garage

No customizing your finishes. The unit is READY TO OCCUPY!

Financing? (possibly up to $2,000 incentive) Click here. Insurance? (possible rates under $1750.00) Click here.

Phase 1 to 5.jpg

Call Carolyn 850-685-4013

ALL Phases are SOLD OUT

Phase Five Closed and Occupied Front Entry Garage A Six unit Building

Interior LOTS 74, 75, 76, 77 End LOTS 73 and 78

Phase Three Closed and Occupied Front Entry Garage An Eight unit Building

Interior LOT(S) 32, 33, 34, 35, 36, 37 End LOT(S )31 and 38

Phase Four Closed and Occupied Rear Entry Garage An Eight unit Building

Interior LOTS 46, 47, 48, 49, 50, 51 End LOTS 45 and 52

Phase Two Closed and Occupied Front Entry Garage A Six unit Building

Interior LOTS 40, 41, 42, 43 End LOTS 39 and 44

Phase One Closed and Occupied Front Entry Garage An Eight unit Building

Interior LOTS 80, 82, 81, 83, 84, 85 End LOTS 79 and 86

 
 
 

Development Progress

Twenty-Two Units have Closed and units are being occupied!

Oct 27th Phase 4 Landscaping finished, power meters to be installed in a couple of days, some units have sinks and running water, appliances being installed

Oct 27th Phase 5 Brickwork finished, some garage doors installed, cabinets and doors being installed

Oct 15th Phase 5 Exterior brickwork in progress and interior doors being installed, cabinets soon to be installed

Oct 15th Phase 4 Floor covering being installed, painting of walls and doors done, exterior unit divider installed, Electricity possibly next week

Sept 16th Phase 4 AC systems being installed, painting walls and doors almost done,

Sept 2nd Phase 5 Exterior getting ready for brick and interior sheet ready for patching.

Sept 2nd Phase 3 Exterior almost done, interior finishes ongoing. Possible closing end of the month. .

Sept 2nd Phase 4 Driveway in, Siding almost done, painting started and cabinets going in.

. July 29th Phase 2 UNITS will be Closing in the next 5 days.

July 28th Phase 3 Flooring is in Cabinets and granite is being installed.

. July 28th Phase 4 Exterior siding started, Sheetrock finished starting to prep for painting.

June 6th Phase 3 Driveways Done, Sheetrock is done. Phase 4 Brickwork started and Plumbing and Electrical almost done. . . May 25th Phase 3 Brickwork done and Sheetrock work all most done and exterior siding started. . . . May 24th Phase 1 Frist unit CLOSED, soon owners will be living in units and using the Mail Boxes. . . . March 31st Phase 1 Landscaping started and banister being installed. . . . . March 31st Phase 5 First floor almost complete and Firewall installed. . . . . March 31st Phase 2 Interior doors installation and painting started. Back patio almost complete. . . . March 31st Phase 3 Roof shingle installation delay in the product. Plumbing to start. . . . . March 21st Phase 4 Gables and Porches being constructed. . . March 10th Phase 1 Cabinets being installed. Backyard pavers are in! . . . . March 10th Phase 2 Exterior Siding and Interior Painting started, . , . . March 10th Phase 4 Second floor almost done! . . . . .March 10th Phase 3 Exterior getting ready for Brickwork, Plumbing, Electrical and AC work close to completion. . . February 23rd Phase 1 Driveway and sidewalk Cement completed. Interior doors installation almost complete. . . . . February 23rd Phase 4 Construction started. . . . . February 23rd Phase 2 Brickwork complete, Sheetrock installation started . . . , February 23rd Phase 3 Front Doors installed Brickwork to start, Plumbing installation started. . . . February 23rd Phase 5 Stacking out foundation. . . . . . February 18th Phase 4 Foundation cement poured! . . . February 12th Phase 1 First coat of paint on walls and ceilings. Doors are being installed.

. . . February 12th Phase 2 Brickwork is almost done, insulation being installed. Then sheetrock installed. . . . February 5th Phase 1 Brickwork complete, preparing to cement driveway. Pulling the main electrical wire to the panel. . . . January 20th Phase 4 Continuation of foundation work and water meters installed.

January 20th Phase 2 Roof shingles going on. Electrical, plumbing, and heating and cooling systems installation continue. . January 20th Phase 3 Construction continues. Firewall between units.

January 20th Phase 1 Sheetrock installation and brickwork are almost complete.

January 17th Phase 1 Sheetrock Installation started

January 11th Phase 1 Brickwork continues Phase 2 Plumbing- AC Ductwork continues Phase 3 On Hold Delay in Firewall Sheetrock

January 4th Phase 1 front brickwork started and insulation installed (attic to be blown in once ceiling installed)

December 23rd Phase 1 Insulation and Sheetrock arrived


December 2nd Phase 2 front and back porches on

December 2nd Phase 3 Construction started



November 24th Phase 3 Construction to start next week



November 24th Phase 2 Is taking shape





November 24th Phase 1 Roof is on and interior plumbing and AC installation started



November 6th Phase 1 Front and back doors installed and windows are being installed

November 4th Phase 2 Construction started


October 30th Phase 2 Cement poured!



October 24th Phase 1 Taking shape!



October 21st Phase 3 Utilities installation to Foundation started.



October 21st Phase 2 Foundation is ready for cement.



October 21st Phase 1 Front Tuscan Design taking shape!




October 21st Phase 1 Back covered porch roof installed.




October 16th Phase 1 Front Gables being installed.



October 9th Phase 2 Foundation Plumbing & Electrical work in progress.


October 9th Phase 1 Second Story going up back view.




October 9th Phase 1 Second Story going upfront view.



September 30th Phase 1 common wall between units going









September 19th Phase 1 The Garage and Porch Foundations competed





September 11th Phase 1 Pouring Cement for Foundation

August 18th PHASE 1 Foundation Plumbing & Electrical work in progress.



August 18th PHASE 2 Water meters for Phase 2 - 6 units were installed today!

August 14th PHASE 2 Corner Foundation Survey Marker stack out and ground preparation done.


July 21st Construction Portable Potty installed

 
DSCN4450.JPG
 
DSCN4447.JPG

.

20201021_155901.jpg
20201008_121320.jpg
20200911_075450.jpg
20200823_103915.jpg
20200820_182704.jpg
20200814_181400.jpg
20200803_154840.jpg
20200724_084507.jpg

Due to COVID-19 the Developer is having delays in the Permitting process at the City of Destin. Anticipation/hope is that the foundation of Phase One to be started by the end of July and the foundation of Phase Two to be completed 4 to 6 weeks later.

On May 22, 2020 the distribution power transformers were installed.

COVID-19 IS DELAYING PROGRESS

On March 13, 2020 the Sales Trailer was delivered.And is open by appointment to view lot locations, floor plans, price list, and to view the finishing touches and are available for hands on.

Power Transfomer Installed.jpg
Sales trailer Installed.jpg

In the summer of 2019 the complex infrastructure was inspected, needed improvements fixed and modified to the current 86 unit Townhome complex.

In 2017 the current Developer/Owner Legacy Properties purchase the Land and started to re-approve the land to its current 86 Unit Townhome complex.

In the year 2012 the 7.81 Acres of Land was initial approved for a Multifamily development, the infrastructure, water and sewer lines, underground power lines, drainage lines, and the streets and curbing were completed in that time frame.